jurnal internasional 4

  • Uploaded by: Ilham Nur Azizi
  • Size: 683.2 KB
  • Type: PDF
  • Words: 8,643
  • Pages: 10
Report this file Bookmark

* The preview only shows a few pages of manuals at random. You can get the complete content by filling out the form below.

The preview is currently being created... Please pause for a moment!

Description

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

Contents lists available at ScienceDirect

Journal of King Saud University – Engineering Sciences journal homepage: www.sciencedirect.com

Original article

Using safety system during the design phase to minimize waste in construction projects Kamal Mahfuth a, Amara Loulizi b, Bassam A. Tayeh a,⇑, Khalid Al Hallaq a, Yazan Issa Abu Aisheh c a

Civil Engineering Department, Faculty of Enginnering, Islamic University of Gaza, Gaza, Palestine Civil Engineering - Tunis El Manar University, Laboratory of Materials, Optimization, and Energy for Sustainability (LAMOED), B.P. 37 Le iBelvédère, 1002 Tunis, Tunisia c Civil Engineering Department, Middle East University, Jordan b

a r t i c l e

i n f o

Article history: Received 7 March 2020 Accepted 17 September 2020 Available online xxxx Keywords: Construction Waste Design phase Safety Safety system

a b s t r a c t Achieving construction projects (CPs) with minimal waste requires not only good construction planning, but also effective management for safety and waste of resources through the project cycle. The aim of this paper is to identify and rank safety factors (SF) during the design phase (DPh) of a project that have positive effects in minimizing waste (cost, time and materials) during its construction. Data and information was gathered from available literature, structured interviews, and questionnaire conducted for 111 randomly selected construction organizations. Triangulation method to enhance the validity and reliability of the study findings was used. The research revealed 18 important SF that had positive effects on minimizing waste in CPs during the DPh. The five most important SF that should be considered to minimise waste are: capabilities and behaviour of the design team in the safety field, appropriateness of quantities and specifications for safety system (SS), appropriateness of foundation system for SS, appropriate public and special conditions for SS and appropriate electrical design for SS. The best linear model was developed on the basis of the importance index of the identified factors. A model was developed to minimize waste in CPs by using SS during the DPh. It is recommended that adequate attention must be given to safety criteria during DPh to minimize resources waste. Ó 2020 The Authors. Production and hosting by Elsevier B.V. on behalf of King Saud University. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).

1. Introduction Safety is a key for increasing productivity and efficiency in CPs. For the completion of CPs at the lowest cost, the highest quality, and the least period, an increased commitment to SS during the DPh must be achieved. The International Labour Organization’s annual report for 2015 indicated that every day, 6300 people die from workplace-related poor safety, resulting in 2.3 million annual deaths, while 317 million accidents of various types occur annually. Additionally, the human cost of this daily challenge is enormous, and the economic burden of poor occupational safety and health (OSH) practices is up to 4% of the annual global gross domestic product (GDP) (Gonzalez-Delgado et al., 2015). Therefore, ⇑ Corresponding author. E-mail address: [email protected] (B.A. Tayeh). Peer review under responsibility of King Saud University.

Production and hosting by Elsevier

it is necessary to incorporate safety into construction plans, to protected worker health, minimized costs, and increased value. This is confirmed by a large number of studies (Ghosh and Young-Corbett, 2009; Nordlöf et al., 2015; Nahmens and Ikuma, 2009, 2012; Nahmens and Mullens, 2011; Tayeh et al., 2020). On the other hand, waste can affect success of CPs and has major impact on construction in terms of productivity, sustainability, time, cost and environment (Abarca-Guerrero et al., 2017; Zhao et al., 2010; Ali et al., 2013; Tayeh et al., 2019). Activists of construction waste management (CWM) are innate through the whole-cycle of a CP from the design until demolition. Construction waste (CW) is usually clustered into two types: physical and nonphysical (Nagapan et al., 2012; Asgari et al., 2017) Physical CW consists from materials including land excavation, clearance, building renovation, demolition and roadwork (Katz and Baum, 2011; Mahfuth et al., 2019). Non-Physical CW are cost overrun and extra time for a CP including any inefficiency in the use of money, equipment, materials labour as waiting time and unnecessary movement of labours (Nazech et al., 2008; Formoso et al., 2002). Over the past few years, the concept of prevention through design (PtD) has emerged. This concept relies on applying methods

https://doi.org/10.1016/j.jksues.2020.09.006 1018-3639/Ó 2020 The Authors. Production and hosting by Elsevier B.V. on behalf of King Saud University. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).

Please cite this article as: K. Mahfuth, A. Loulizi, B.A. Tayeh et al., Using safety system during the design phase to minimize waste in construction projects, Journal of King Saud University – Engineering Sciences, https://doi.org/10.1016/j.jksues.2020.09.006

K. Mahfuth, A. Loulizi, B.A. Tayeh et al.

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

of end users, third parties, and construction workers (Culvenor et al., 2007; Bansal, 2011; Micheli et al., 2018).

early in the design process that would maximize safety later on. PtD encourages the thought for safety concepts during the design stage. Hence, PtD requires designers to spend efforts on anticipating and designing out threats to workers who will execute the designs (wang et al., 2014). The research described in this paper falls into the PtD concept. Indeed, the research team believes that it is possible to find safety features during the DPh that would minimize CW, both physical and non-physical, while constructing the project. The research seeks the relationship between SS and waste in CPs by identifying and ranking SF that have the most positive effects on waste minimization in CPs during the DPh and builds a model based on these factors to minimize CW by using SS.

2.2. DFCs around the globe In the US, the American Society of Civil Engineers (ASCE) believes that increasing safety in CPs requires commitment from all involved legs. The ASCE and the National Association of Professional Engineers state in their code of ethics that designers should have ethical obligations towards safety, and health of the public and should take action even if the hazard is not imminent. DfCS will increasingly progress in the US through: facilitate prefabricated construction, select systems and materials that are safer than other alternatives, perform construction engineering, and apply spatial considerations to minimize construction hazards (Toole and Gambatese, 2008). In the European Union, whilst designers previously had some responsibilities for minimizing risk under common law provisions, the Temporary and Mobile Construction Site Directive was the first explicit legislation that placed duties on designers (Aires et al., 2010). It requires designers to take working conditions during construct, maintenance and demolition work into account in their designs. Its key concern is planning and coordination of construction activities through improved transfer of information between all parties involved in DPh of projects (Bluff, 2004; Kawuwa et al., 2018). Construction (design and management) regulations place duties for addressing construction workers’ safety and health on designers. It places a duty on the designer to ensure that any design should avoid unnecessary foreseeable risks to workers (Toole and Gambatese, 2008). Nonetheless, Behm (2005a) cited that the success of the construction design management (CDM) in reducing construction fatalities has been difficult to establish since designers in the UK has been slow in meeting their responsibility under the construction regulations. Brace et al. (2009) found that after fifteen years of CDM, many designers still believe it is not related to them. Even the small groups who want to engage are having difficulty doing this. The designers in the UK often treat OSH plans merely as a paperwork requirement. In South Africa, designers are required to make available all relevant information about the design, communicate hazards to contractors, and modify design or use a substitute material to improve worker safety (Smallwood, 2008).

2. Literature review The literature search included both standard approaches (databases’ searches such as ScienceDirect, Google Scholar, TRIS, etc.) as well as the research team extensive contacts, both domestic and abroad, to find data and pertinent citations that have not been formally published on the topic. The literature searches included journals’ and conferences’ papers as well as books. The data addressed the practices and concepts of construction safety (CS) and CWM, and the SF having positive effects on minimizing CW through DPh. 2.1. Design for construction safety (DfCS) concept Safety management system is comprehensive and a systematic business method to managing safety risks. It must contains policy of safety, planning, control, communication, training and incentives for employee participation (Muñiz et al., 2007). The most hazardous industries are CPs due to the nature of the work resulting from integration of environment, tools and various human factors (Haro and Kleiner, 2008; Nordic council of ministries, 2017). In fact, CPs has one of the highest accident incidence rates compared to other industries (Laitinen and Päivärinta, 2010; Jo et al., 2017). Statistics indicate that CPs is still facing a safety problem. In the US, construction employs 7% of the workers, but accounts for 21% of the injuries (Zarges and Giles, 2008). In the UK, workers in CPs and agriculture account for 46% of total fatal injuries. In British Columbia, the overall injury rate in CPs is more than twice the local average for all industries (Village and Ostry, 2010). Many studies showed that it is possible to reduce (by 40% to 60%) or even eliminate risks and accidents by addressing safety through DPh and if DfCS concept have been utilized (Frijters and Swuste, 2008; Behm, 2005; Gambatese, 2008; Rwamamara and Holzmann, 2007; Toole et al., 2006; Manuele, 2008; Malekitabar et al., 2016). In addition, Manuele (2008) stated that by applying DfCS concept, the benefits that could be obtained are increased productivity, minimized operating costs, significant risk and expensive retrofitting. DfCS concept is a collaborative process, where designers benefit from field experience to produce designs that could be executed safely. DfCS is defined as the safety consideration in construction site in DPh of CPs with the goal of minimizing the inherent risks to construction worker (Toole et al., 2006; Orihuela et al., 2017). Design decisions related to design, construction methods and materials used should incorporate the consideration of worker safety during projects cycle. The opportunities to address worker safety in this phase are considerable where it is possible to design out hazards and/or integrate risk control measures that comply with the original design concept and structural and functional requirements of CP. The success of DfCS concept depends upon the joint effort among all parties involved in CP in addition to researchers and educators’ efforts. From an ethical point of view, designers should accept this responsibility to ensure the wellbeing

2.3. DfCS suggestions The literature mentions many DfCS suggestions that if considered by designers through the DPh could enhance worker safety during the implementation and maintenance phases. Many individuals and organizations reported several DfCS suggestions that cover different engineering fields and types of engineering projects (Work Safe Victoria, 2005, 2007; Behm, 2006; European Federation of Engineering Consultancy Associations, 2006; Toole et al., 2006; Hinze and Marini, 2008; Kawuwa et al., 2018). The DfCS suggestions are related to project position and layout, material selection, contractor storage places, mechanical and electrical installations, falling from heights, trenches, communicating hazards to contractors, sequence of work and maintenance requirements regarding safety, construction documentation, and work schedule (Al-Hajj and Hamani, 2011). Many researchers reported different SF that minimize construction waste such as project site, project plan, detailed design, procurements, technologies, designers capacities, behaviour and attitude, and external mechanism (Bluff, 2004; Work Safe Victoria, 2005, 2007; Behm, 2006; European Federation of Engineering Consultancy Associations, 2006; Toole et al., 2006; Rwamamara and Holzmann, 2007; Hinze and Marini, 2008; Zarges and Giles, 2008; Durdyev et al., 2017). 2

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

K. Mahfuth, A. Loulizi, B.A. Tayeh et al. Table 1 Ques. content.

3. Research methodology Triangulation method, through cross verification from these three sources, was used to enhance the validity and reliability of the study findings. The methodology was summarized in Fig. 1. A questionnaire (Ques.) distributed to 111 construction companies. The Ques. was divided into three main parts as shown in Table 1. The structured interviews with professional engineers was performed. During all interviews, the questions were given in the same order and wording. Additionally, observations of CPs and site documentary sources as site instructions, safety plan, meeting, drawings, and progress reports were consulted. Then, in order to test the appropriateness, reliability and validity of the used scales for some of the questions, a pilot study was undertaken in two procedures. In the first, face-to-face interviews with 15 experts, projects mangers, and engineers from different contracting companies were conducted. In the second procedure, 15 professionals reviewed the draft Ques. All invited professionals had more than 10 years of experience in CP. Some of them were academians while others were professionals. The interviews as well as the pilot study helped in identifying problems in the draft Ques. In addition, many of the given questions were improved in terms of their wordings for better understanding and to avoid misinterpretation and possible different readings for the same question. The interviews and the pilot study were very helpful in filtering SF that have positive effect on minimizing CW during DPh. In fact,

Section

Variables

Part 1: Profile of respondent Respondent Organization and personality Study the relations based on characteristic of respondent type between DfCS and minimizing CW. Part 2: Safety practice in CPs Safety management practices Respondent position,

Objective Respondent type, Company classification, Numbers and value of CPs qualification, classification and experience.

Data record, Safety plan, producers, training, regulation and law of safety

To highlight management practices the safety in CPs Commitment degree to SS Determine the commitment SF have SF have effect on waste in and the effect of DfCS on impacts on CPs during DPh reducing CW then ranking it minimizing according its RII. the CW Part 3: respondent recommendations to reducing CW by using SS in CPs

the professionals were asked to give their opinion about the SF found in the literature and were welcomed to add other possible SF based on their experience. All collected data was then taken into a final version of the Ques., which was then distributed to the target group.

Fig. 1. Methodology flowchart. 3

K. Mahfuth, A. Loulizi, B.A. Tayeh et al.

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

3.1. Study population and sample size

Table 3 SF during DPh identified as having positive effects on minimizing CW.

The target group included contracting companies, consulting offices, owners and donors’ agencies. Contracting companies, which are registered in the country’s contractors’ union and classified by the ‘‘National Classification Committee” (NCC) to have valid registration were targeted in this study. Only companies that are classified according to the NCC as ‘‘first class” were sought; the other classes of companies were neglected due to their low practice in CS and waste management as well as their limited administration experience. In total, 66 active companies exist in the country that met the study target criteria. For the consulting offices, 68 offices, which are registered in the country’s engineers syndicate were targeted. The owner agencies, with a total of 15, consist of all ministries, municipalities, international agencies, Non-governmental organizations (NGOs), and public project owners. Ten active donors’ agencies were also contacted. The total sample size needed for this research determined by Eq. (1), while Eq. (2) was used to correct the outcome of Eq. (1) for finite population (Casella and Berger, 2002).



Snew

Z 2  P  ð1  PÞ

#

Factor

Number of Paragraphs

F1 F2 F3 F4

Appropriate project site for SS Appropriate project planning for SS Appropriate choice of quality materials for SS Appropriate choice of lengths, sizes and dimensions for the SS Appropriate staircase design for SS Appropriate foundation system for SS Appropriate structural design system for SS Appropriate protection edges & height areas for SS Appropriate movement from and to the site for SS Appropriate design of scaffolding work for SS Appropriate design of the openings for SS Appropriate electrical design for SS Appropriate mechanical design for the SS Appropriate plan and drawing for SS Appropriate public and special conditions for SS Appropriate schedule for SS Appropriate quantities and specifications for SS The capabilities and behaviour of the design team in the safety field

5 4 7 7

F5 F6 F7 F8 F9 F10 F11 F12 F13 F14 F15 F16 F17 F18

4 4 14 2 3 4 3 15 10 8 5 17 4 8

ð1Þ

C2 SS ¼ 1 þ SS1 pop

Table 4 Paragraphs used under factor F18.

ð2Þ

where S is the sample size; Z is the Z-value from the normal distribution table, taken as 1.96 that corresponds to 95% confidence interval; P is the percentage picking a choice, expressed as decimal (assumed to be 0.50); and C is the maximum error of estimation (assumed to be 0.08). Using Eq. (1) with the assumed values, a population size of 150 is obtained. This number is reduced using Eq. (2) and the resulting values are shown in Table 2 for the different types of contacted companies and agencies. The figure shows also the number of returned Ques. with the % responses. In total, 111 filled Ques. were returned to the study team and were all used for analysing the responses (Casella and Berger, 2002).

1.

High educational background of the designer on the OSH

2. 3. 4.

High work experience of the designer at safety field Simplifying the design and avoiding complexity High awareness of the designer of the environmental requirements, the regulations and the laws related Good coordination between all members of the design team Prepare full and detailed plans for all works with high quality and without having a lack of design information The design team should know the machines available to local contractors to implement the project on this basis The design team should understand implementation methods, and plans which can be implemented in reality

5. 6. 7. 8.

Linear regression model, Effect size (ES). For more detail, refer to Probability and Statistics Cookbook (Vallentin, 2011). In addition, the relative importance index (RII) was used to determine the ranks of all Ques. RII was computed using Eq. (3).

3.2. Factors of SS during DPh and its impact on minimizing CW in CPs From the literature review, structured interviews, and pilot study, 18 factors of SS during the DPh were identified as having impact on minimizing CW. Table 3 shows these factors. The table shows also the number of paragraphs used under each of these evaluated factors. For example, Table 4 shows the paragraphs considered for factor F18 (The capabilities and behaviour of the design team in the safety field).

P

RII ¼

W  100% AN

ð3Þ

where W is the weighting given to each factor by the respondents, A is the highest weight (10 in this research), and N is the total number of respondents. RII value has a range from 0 (0 not inclusive) to 100%, the higher the value of RII, the more impact of the attribute.

3.3. Data measurement and analysis 4. Research findings and discussion The collected data was analysed using both descriptive and inferential statistical tools. All Ques. results were input into Statistical Package for the Social Sciences (SPSS 22). 9 types of data analysis techniques were used in this paper as follows: Frequency analysis, Spearman brown, Pearson correlation coefficients, Smirnov test, One sample t-test, Independent samples t-test, ANOVA,

4.1. General information about the institutions and participants Table 5 shows the distribution of the organizations who participated in this research. It is noted that the sample included all parties directly related to the design activities: the consultant as the

Table 2 Sample size and determination. Type

Total

Sample size by using Eq.

Distributed

Returned

Percentage of responding

Contracting company ”first class” Consulting offices Owner agencies Donors agencies

66 68 15 10

46 47 14 10

50 50 15 10

42 48 11 10

84% 96% 73.3% 100%

4

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

K. Mahfuth, A. Loulizi, B.A. Tayeh et al. Table 5 General information about the institution and the participant. Variables

Variable items

Frequency

Percentage%

Organization Classification

Owner Donner/Mediator Contactor Consultant office Total Buildings

11 10 42 48 111 First Second First Second First Second First

42 0 35 6 27 9 24

9.9 9.0 37.9 43.2 100.0 100 0.0 85.4 14.6 75.0 25.0 66.7

<3 14 <10 projects

Second between 3 and<10 17 between 10 & <15

12 between 10 & <15 23 between 15 and<20

21 <15 labors 14

27 between 15 & <30 12

24 between 30 and<50 21

33.3 more than 15 57 more than 20 projects 39 more than 50 64

Diploma 1 civil 90 <5 7 37

bachelor 45 architectural 8 between 5 to<10 37 32

master 63 mechanic 7 between 10 to<15 30 26

doctorate 2 electronic 6 more than 15 37 16

43

47

11

10

No coursing 19 36 <2

only one course 40 29 between 2 to <4

three or more 23 6 more than 6

18 <5

20 between 5 and <10 28

two courses 29 13 between 4 and <6 million 15 between 10 and <15 24

33

Work field and Classification of contractors

Roads Water &Sewage* Electro mechanic* Organization C.P value through last 5 years (by million) Organization C.P number through last 5 years

Average labors number per day through year Qualification for the participant

Scientific specialization for the participant (engineering) Experience (year) for the participant In construction field in CS field in CWM Training courses for the participant in CS in CWM Projects value (million) supervised by the participant through last 5 years Projects number supervised by the participant through last 5 years

26

58 more than 15

tributed. Table 6 presents some of the results for this test for some fields used in the Ques. Two statistical tests were performed to insure the validity of the Ques.: the first test is Pearson test to measure the correlation coefficient (R) between each paragraph in one field and the whole field (Internal validity). The second test is structure validity test (Pearson test) to test the validity of the Ques. structure by testing the validity of each field and the validity of the whole Ques. (Structure validity). It measures R between one field and all the fields of the Ques. that have the same level of similar scale. The test resulted in R of each paragraph of DPh during DPh significant at a = 0.05, so it can be said that the paragraphs of this field are consistent and valid to measure what it is set for. Table 7 presents some of

designer and supervisor, the contractor as the executor and the owner as a beneficiary and financier. Therefore, the opinions of all parties involved in a construction project were collected in this paper. Furthermore, the experts that participated in this study have academic and practical cultural and scientific diversity, which gives the results of the study a universal aspect.

4.2. General findings about the questionnaire questions The Kolmogorov-Smirnov (KS) test of normality resulted in pvalues greater than the 0.05 level of significance, which means that each field of DPh in CPs could be assumed to be normally dis-

Table 6 Results of the KS test of normality. Field

Statistic

df*

p-value

Safety management practice in CPs SF related to effect on reducing the CW during DPh

0.054 0.048 0.041 0.085 0.075 0.084 0.055

111 111 111 111 111 111 111

0.200 0.200 0.200 0.069 0.161 0.051 0.200

Degree of commitment Materials waste Time overrun Cost overrun

CWM in construction projects Degree of commitment to reduce CW during DPh *

Degrees of freedom. 5

K. Mahfuth, A. Loulizi, B.A. Tayeh et al.

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

Table 7 R of each paragraph of two of the DPh factors. No.

Commitment degree

Waste in material

R

R

p-value

F1: Appropriate of the project site for the safety system P1 0.847 0.000 0.784 P2 0.867 0.000 0.788 P3 0.906 0.000 0.769 P4 0.770 0.000 0.706 P5 0.687 0.000 0.479 F2: Appropriateness of project planning for the safety system P1 0.640 0.000 0.940 P2 0.910 0.000 0.940 P3 0.846 0.000 0.948 P4 0.937 0.000 0.947

Time overrun

Cost overrun

p-value

R

p-value

R

p-value

0.000 0.000 0.000 0.000 0.007

0.910 0.741 0.920 0.906 0.586

0.000 0.000 0.000 0.000 0.001

0.609 0.596 0.815 0.858 0.465

0.000 0.001 0.000 0.000 0.010

0.000 0.000 0.000 0.000

0.796 0.891 0.739 0.830

0.000 0.000 0.000 0.000

0.827 0.946 0.935 0.976

0.000 0.000 0.000 0.001

to these factors, as the sign of the test is positive (RII greater than 60%). Table 8 shows RII and rank of the SF during DPh. The highest ranked in minimizing waste of materials is factor no. 18 ‘‘The capabilities and behaviour of the design team in the safety field” with RII (83.90%) and p-value<0.001. also this factor had the highest ranked in minimizing waste of time, while ranked as the third factor in minimizing cost overrun. This result is in agreement with findings from previous studies (Frijters and Swuste, 2008; Gambatese et al, 2008; Manuele, 2008) that confirm that DFSC reduces accidents by (40%  60%) during the project cycle. The importance of this factor in reducing waste is highlighted for its Association with high scientific knowledge, educational background and practical experience of the designers on the OSH. High awareness of the designers about safety requirements as well as its related regulations and laws, makes the design team, by the ethical issue, simplify the design and avoid complexity, thus reducing accidents, financial compensation during implementation and accelerates the execution, thereby saving time and materials. The above results are in agreement with those of Culvenor et al, 2007. The good coordination between all members of the design team to prepare full and detailed plans for all works with high quality and without having a lack of design information results on minimizing waste in material, time, and cost. In addition, if the design team knows the machines available with the contractors to implement the project, understand implementation methods, and plans, the waste in material, time, and cost will be reduced. The second highest ranked in minimizing waste (cost, time and materials) is factor no. 17 ‘‘Appropriate quantities and specifica-

this test results for the first two considered factors and their respective paragraphs. 4.3. Testing of the hypotheses The hypotheses were tested in this paper are , as following: ‘‘there is an inverse relationship, statistically significant at a = 0.05, between commitment to DfCS and waste in (time, cost overrun, material overrun) in CPs”. Parametric tests were used to perform the hypotheses testing of the study. The output of these test approved all hypotheses so there is an inverse relationship, statistically significant at a  0.05, between commitment to DfCS during DPh and waste (cost, time and materials) in CPs. 4.4. Main factors of SS that have positive impacts on minimizing CW during DPh Table 8 Summarizes the main SF related to positive impacts on reducing waste of cost, time and materials during DPh. The highest factor ranked in minimizing waste in (materials and time) is ‘‘The capabilities and behaviour of the design team in the safety field” but the highest factor ranked in minimizing waste in cost is ‘‘Appropriate movement from and to the site for SS”. While the lowest ranked in minimizing waste in materials is ‘‘appropriate protection edges and height areas for SS” but the lowest ranked in minimizing waste in time is ‘‘appropriate design of the opening for SS” finally the lowest ranked in minimizing waste in cost is ‘‘appropriate structural design system for SS”. The respondents agreed Table 8 RII and rank of the SF during design phase. Factors

F1 F2 F3 F4 F5 F6 F7 F8 F9 F10 F1111. F12 F13 F14 F15 F16 F17 F18

Commitment to SS

Waste in material

Waste in time

Waste in cost

RII

p-value (Sig.)

ES

RII

p-value (Sig.)

ES

RII

p-value (Sig.)

ES

RII

p-value (Sig.)

ES

80.30 80.74 81.46 79.93 86.77 83.78 76.38 78.06 82.25 79.16 80.18 82.40 80.80 73.88 83.71 76.89 86.77 81.90

<0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

1.47 1.50 1.80 1.64 2.30 1.85 1.52 1.32 1.74 1.35 1.63 2.41 1.75 0.72 1.69 1.27 2.20 2.01

74.05 75.29 74.34 74.99 76.78 80.90 74.86 73.19 74.08 75.81 74.53 76.93 76.14 73.24 78.28 75.20 81.14 83.90

<0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

1.10 0.92 0.90 1.31 0.87 1.64 1.38 0.90 0.87 1.12 0.97 1.52 1.28 0.83 1.28 1.28 1.56 1.24

76.23 77.09 73.54 73.88 75.74 80.63 73.04 73.15 75.55 76.57 71.92 77.65 75.76 75.02 79.92 75.87 81.30 82.08

<0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

1.29 1.28 0.93 1.18 0.90 1.61 1.24 0.67 1.09 1.26 0.75 1.57 1.24 0.96 1.46 1.48 1.45 2.40

77.58 75.87 76.15 75.08 76.28 80.51 71.06 72.47 84.05 75.99 73.57 75.84 75.83 73.86 80.27 76.46 83.51 82.66

<0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

1.60 1.07 1.31 1.36 1.02 1.66 0.91 0.85 2.02 1.18 0.84 1.37 1.23 0.81 1.46 1.23 1.82 2.38

6

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

K. Mahfuth, A. Loulizi, B.A. Tayeh et al.

these elements do not require special attention during the design stage, and the resulting risk can be reduced by using safety equipment during the implementation phase.

tions for SS” with RII (81.14%, 81.30% and 83.51% respectively) and p-value<0.001. This result is very realistic. Materials and their specifications represent the largest proportion of the cost of any project and are closely associated with the project completion period. The agreement between bill of quantities, technical specifications and the precise characterization of the materials to be safe and good quality, reduce the wastes, which may result from supplying extra quantities or non-conforming to specifications. Using hazard materials need a special condition in storing and implementation. The above is compatible with Toole et al., 2008 and Aires et al., 2010. The third highest ranked in minimizing waste (materials- time) is factor no. 6 ‘‘Appropriate foundation system for SS” with RII (80.90% and 80.63% respectively) and p-value<0.001. This result agreed with Nangan et al., 2017. The importance of this factor lies in conduct site investigation to examine the need of shoring system for temporary excavations and the appropriate foundation system. Foundation failure is caused by multiple reasons as drainage problems, poor soil preparation, plumbing issues, dry heat and large trees (factor related to safety in design phase). Design for safety concept requires accurate structural analysis as well as the in-depth review of the supporting soil. Fortunately, the failure of modern radical foundations is rare. This is significant because of the recognized need to analyse and test the correct geological location as well as to improve foundation design. On the other hand, knowing the tools and equipment available locally with contractors should minimize waste which may result from extra excavation, landfill, shuttering, and levelling (Shash and Ghazi, 2003) The fourth highest ranked in minimizing waste (materialstime) is factor no. 15 ‘‘Appropriate public and special conditions for SS” with RII (78.28% and 79.92% respectively) and pvalue<0.001. This result agreed with Cenovus, 2017. The importance of this factor lies in its containment: (1) the requirements of occupational health and safety for all the work, and the mandatory of its implementation; (2) the necessity of providing prevention and safety equipment by the contractor; (3) providing health and safety plan by the contractor and it should be approved by the supervisor and the relevant authorities; and (4) clear penalty clauses for each violation of any condition of the safety conditions in the site. This factor contains all requirements from contractors and their subcontractors to support OSH commitments, approaches and goals (Enshassi, et al., 2012). It is imposed on the contractor to develop and implement such, practices, procedures, programs, policies, training, guidelinesand other documentation to effectively meet or exceed safety requirements. If the contractor would commit in the implementation phase to the above safety requirements, it will inevitably result in no accidents or injuries and will effectively contribute to reducing waste. The fifth highest ranked in minimizing waste (materials- time) is factor no. 12 ‘‘Appropriate electrical design for SS” with RII (78.28% and 79.92% respectively) and p-value<0.001. The result is compatible with that of Wong et al., 2018. Electrical installations are key activities in all CPs. Electrical works includes installation and maintenance of electrical wiring, air-conditioning system, fire services system, lift and escalators, and drainage and plumbing system. It involves lots of high-risk activities, for examples, welding, using handheld tools, etc. so electrical safety is a vital issue in promoting CS. The lowest ranked factor in minimizing waste in materials is factor no.8 ‘‘Appropriate protection edges & height areas for SS” with RII (73.19%) and p-value<0.001. The lowest ranked factor in minimizing waste in time is factor no.11 ‘‘Appropriate design of the openings for SS” with RII (71.92%) and p-value<0.001. The lowest ranked factor in minimizing waste in cost is factor no.7 ‘‘Appropriate structural design system for SS” with RII (71.06%) and pvalue<0.001. The explanation of these results lies on the fact that

4.5. Prediction equations The best linear models relating variables (commitment to safety system during DPh and minimizing waste (materials time and cost) in CPs, based on the results of the Ques. were developed. Fig. 2 shows, for example, the results obtained, for ‘‘minimizing waste of materials” as a function of ‘‘commitment to DFCS”, ‘‘minimizing waste of time” as a function of ‘‘commitment to DFCS”, and ‘‘minimizing waste of cost” as a function of ‘‘commitment to DFCS”. The equations obtained, shown in Table 9, are used as predictive equations to minimize waste (materials, time and cost) according to the degree of commitment to each factor of SS during DPh. There is statistical significant relationship at (a < 0.05) between commitment to DFCS and minimizing CW in (material- time- cost) through DPh. For example, the relation between the appropriateness of the project planning for SS and minimize CW in: material equals 0.457, that for time is equal to 0.308, and that for cost is equal to 0.375. This result means that there is positive relationship between commitment to DFCS and minimizing CW. The coefficient of determination, R2, equals 0.209 for material, 0.095 for time, and 0.141 for cost. This means that 20.9%, 9.5% and 14.1% of the variability of commitment to the appropriateness of the project planning for the SS is due to minimize CW in materials, time and cost, respectively. Since the found p-value are<5%, reducing CW has significant positive effect on the degree of commitment to DFCS. Table 9 presents the prediction equations relating commitment to all the factors studied in this research with the three types of CW (Material, time, and cost). 5. Conclusions and recommendations This study identified and ranked 18 SF and their positive effects on reducing waste (materials, time and cost) in Cps during DPh and the following are the conclusions:  The five most important factors to be considered in minimizing material and time wastage are: capabilities and behaviour of the design team in the safety field, appropriateness of quantities

Fig. 2. Appropriateness of the project planning for safety system. 7

K. Mahfuth, A. Loulizi, B.A. Tayeh et al.

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

Table 9 Predictive equations to minimize waste according to the degree of commitment to each factor of SS during DPh. Commitment

Material

Appropriate project planning for SS

r r2 Y ¼ 4:018 þ 0:422X std 0:641 0:079 sig 0:000 0:000 r r2 Y ¼ 1:775 þ 0:713X std 0:750 0:092 sig 0:020 0:000 r r2 Y ¼ 0:429 þ 0:860X std 0:795 0:097 sig 0:591 0:000 r r2 Y ¼ 2:046 þ 0:682X std 0:506 0:063 sig 0:000 0:000 r r2 Y ¼ 0:198 þ 0:862X std 1:177 0:134 sig 0:867 0:000 r r2 Y ¼ 1:446 þ 0:793X std 0:483 0:057 sig 0:003 0:000 r r2 Y ¼ 2:492 þ 0:654X std 0:557 0:072 sig 0:000 0:000 r r2 Y ¼ 3:186 þ 0:530X std 0:699 0:088 sig 0:000 0:000 r r2 Y ¼ 1:705 þ 0:693X std 0:843 0:101 sig 0:046 0:000 r r2 Y ¼ 4:056 þ 0:445X std 0:683 0:085 sig 0:000 0:000 r r2 Y ¼ 2:794 þ 0:581X std 0:826 0:102 sig 0:001 0:000 r r2 Y ¼ 2:750 þ 0:581X std 0:819 0:099 sig 0:001 0:000 r r2 Y ¼ 2:345 þ 0:652X std 0:650 0:080 sig 0:000 0:000 r r2 Y ¼ 2:877 þ 0:602X std 0:413 0:054 sig 0:000 0:000 r r2 Y ¼ 2:938 þ 0:584X std 0:672 0:079 sig 0:000 0:000 r

Appropriateness of the project site for SS

Appropriate choice of quality materials for SS

Appropriate choice of lengths, sizes and dimensions for SS

Appropriate staircase design for SS

Appropriate foundation system for SS

Appropriate structural design system for SS

Appropriate protection edges and height areas for SS

Appropriate movement from and to the site for SS

Appropriate scaffolding work for SS design

Appropriate design of the openings for SS

Appropriate electrical design for SS

Appropriate mechanical design for SS

Appropriate plan and drawing for SS

Appropriate public and special conditions for SS

Appropriate schedule for SS

Time

8

0.457 0.209

0.598 0.357

0.649 0.421

0.722 0.522

0.523 0.274

0.800 0.640

0.655 0.429

0.499 0.249

0.548 0.301

0.449 0.201

0.480 0.230

0.503 0.253

0.617 0.381

0.729 0.532

0.577 0.333

0.695

r r2 Y ¼ 5:367 þ 0:281X std 0:677 0:083 sig 0:000 0:001 r r2 Y ¼ 5:625 þ 0:506X std 0:640 0:078 sig 0:000 0:000 r r2 Y ¼ 2:222 þ 0:630X std 0:824 0:100 sig 0:008 0:000 r r2 Y ¼ 1:813 þ 0:698X std 0:525 0:065 sig 0:001 0:000 r r2 Y ¼ 1:644 þ 0:683X std 1:118 0:128 sig 0:144 0:000 r r2 Y ¼ 2:535 þ 0:660X std 0:603 0:071 sig 0:001 0:000 r r2 Y ¼ 2:524 þ 0:626X std 0:548 0:071 sig 0:000 0:000 r r2 Y ¼ 2::444 þ 0:6X std 0:976 0:123 sig 0:014 0:000 r r2 Y ¼ 2:222 þ 0:648X std 0:720 0:087 sig 0:003 0:000 r r2 Y ¼ 4:433 þ 0:407X std 0:641 0:080 sig 0:000 0:000 r r2 Y ¼ 2:588 þ 0:574X std 0:885 0:109 sig 0:004 0:000 r r2 Y ¼ 3:060 þ 0:571X std 0:841 0:101 sig 0:000 0:000 r r2 Y ¼ 1:967 þ 0:694X std 0:630 0:077 sig 0:002 0:000 r r2 Y ¼ 3:100 þ 0:596X std 0:404 0:053 sig 0:000 0:000 r r2 Y ¼ 3:058 þ 0:589X std 0:629 0:074 sig 0:000 0:000 r

Cost 0.308 0.095

0.527 0.278

0.516 0.266

0.717 0.514

0.456 0.208

0.664 0.441

0.645 0.416

0.437 0.191

0.583 0.340

0.440 0.193

0.450 0.202

0.475 0.225

0.653 0.426

0.733 0.538

0.606 0.367

0.691

r r2 Y ¼ 5:358 þ 0:299X std 0:576 0:071 sig 0:000 0:000 r r2 Y ¼ 2:974 þ 0:571X std 0:705 0:086 sig 0:000 0:000 r r2 Y ¼ 2:961 þ 0:571X std 0:679 0:082 sig 0:000 0:000 r r2 Y ¼ 2:638 þ 0:609X std 0:526 0:065 sig 0:000 0:000 r r2 Y ¼ 2:020 þ 0:646X std 1:009 0:115 sig 0:048 0:000 r r2 Y ¼ 3:827 þ 0:504X std 0:666 0:079 sig 0:000 0:000 r r2 Y ¼ 1:746 þ 0:702X std 0:654 0:085 sig 0:009 0:000 r r2 Y ¼ 2:774 þ 0:573X std 0:681 0:086 sig 0:000 0:000 r r2 Y ¼ 1:666 þ 0:819X std 0:355 0:043 sig 0:000 0:000 r r2 Y ¼ 4:619 þ 0:376X std 0:673 0:084 sig 0:000 0:000 r r2 Y ¼ 3:206 þ 0:518X std 0:932 0:115 sig 0:001 0:000 r r2 Y ¼ 2:706 þ 0:592X std 0:865 0:104 sig 0:002 0:000 r r2 Y ¼ 2:353 þ 0:647X std 0:677 0:083 sig 0:001 0:000 r r2 Y ¼ 2:561 þ 0:653X std 0:434 0:057 sig 0:000 0:000 r r2 Y ¼ 2:939 þ 0:608X std 0:633 0:075 sig 0:000 0:000 r

0.375 0.141

0.537 0.288

0.553 0.306

0.667 0.445

0.473 0.224

0.523 0.274

0.621 0.386

0.538 0.290

0.879 0.772

0.396 0.157

0.396 0.157

0.478 0.228

0.599 0.359

0.740 0.547

0.615 0.378

0.640

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

K. Mahfuth, A. Loulizi, B.A. Tayeh et al. Table 9 (continued) Commitment

Appropriate quantities and specifications for SS

The capabilities and behaviour of the design team in the safety field

Material

Time

r2 Y ¼ 2:746 þ 0:621X std 0:480 0:061 sig 0:000 0:000 r r2 Y ¼ 3:074 þ 0:581X std 0:794 0:091 sig 0:000 0:000 r r2 Y ¼ 2:839 þ 0:678X std 1291 0:156 sig 0:030 0:000

and specifications for SS, appropriateness of foundation system for SS, appropriate public and special conditions for SS and appropriate electrical design for SS.  The five most important factors affecting cost efficiency are: appropriate movement from and to the site for SS, appropriateness of quantities and specifications for SS, capabilities and behaviour of the design team in the safety field, appropriateness of foundation system for SS and Appropriate public and special conditions for SS.  Based on the statistical tests and the relative important factors, a model was constructed showing the relationship between degrees of commitment to the safety system and minimizing waste (materials, time and cost) in construction projects during design phase.

0.483

0.523 0.274

0.384 0.147

r2 Y ¼ 3:289 þ 0:559X std 0:437 0:056 sig 0:000 0:000 r r2 Y ¼ 3:390 þ 0:546X std 0:898 0:102 sig 0:000 0:000 r r2 Y ¼ 4:685 þ 0:430X std 0:574 0:070 sig 0:000 0:000

Cost 0.477

0.455 0.207

0.510 0.260

r2 Y ¼ 2:676 þ 0:646X std 0:580 0:074 sig 0:000 0:000 r r2 Y ¼ 2:556 þ 0:668X std 0:693 0:079 sig 0:000 0:000 r r2 Y ¼ 4:739 þ 0:431X std 0:604 0:073 sig 0:000 0:000

0.409

0.629 0.396

0.492 0.242

References Abarca-Guerrero, L., Maas, G., Van Twillert, H., 2017. Barriers and motivations for construction waste reduction practices in Costa Rica. Resources 6 (4), 69. Aires, M.D.M., Gámez, M.C.R., Gibb, A., 2010. Prevention through design: The effect of European Directives on construction workplace accidents. Safety Sci. 48 (2), 248–258. Al-Hajj, A., Hamani, K., 2011. Material waste in the UAE construction industry: Main causes and minimization practices. Arch. Eng. Des. Manag. 7 (4), 221–235. Ali, H.A.E.M., Al-Sulaihi, I.A., Al-Gahtani, K.S., 2013. Indicators for measuring performance of building construction companies in Kingdom of Saudi Arabia. J. King Saud Univers.-Eng. Sci. 25 (2), 125–134. Asgari, A., Ghorbanian, T., Yousefi, N., Dadashzadeh, D., Khalili, F., Bagheri, A., Mahvi, A.H., 2017. Quality and quantity of construction and demolition waste in Tehran. J. Environ. Health Sci. Eng. 15 (1), 1–17. Bansal, V.K., 2011. Application of geographic information systems in construction safety planning. Int. J. Project Manage. 29 (1), 66–77. Behm, M., 2005. Linking Construction Fatalities to the Design for Construction Safety Concept. J. Saf. Sci. 43 (8), 589–611. Behm, M., 2006. An Analysis of Construction Accidents from a Design Perspective. The Center of Protect Workers’ Rights, Silver Spring, USA. Bluff, L., 2004. Regulating Safe Design and Planning of Construction Work: A review of Strategies for Regulating OHS in the Design and Planning of Buildings, Structures and other Construction Projects. National Research Centre for Occupational Health and Safety Regulation. Australian National University. Brace, C., Gibb, A., Pendlebury, M., Bust, P. 2009. Phase 2 Report: Health and safety in the construction industry: Underlying causes of construction fatal accidents– External research. London, UK. Casella, G., Berger, R. 2002. Statistical inferences ‘‘second edition”. Florida: aviation of Thomson Learning Inc. Culvenor, J., Cowley, S., Else, D. Hall, S., 2007. Concepts of Accident Causation and their Role in Safe Design among Engineering Students. Paper presented at the 2007 AaeE Conference, Melbourn Durdyev, S., Mohamed, S., Lay, M.L., Ismail, S., 2017. Key factors affecting construction safety performance in developing countries: Evidence from Cambodia. Construct. Econ. Build. 17 (4), 48. Enshassi, A., Faisal, M.A., Tayeh, B., 2012. Major causes of problems between contractors and subcontractors in the Gaza Strip. J. Finan. Manage. Prop. Construct. 17, 92–112. European Federation of Engineering Consultancy Associations & Architects’ Council of Europe. 2006. Designing for Safety in Construction: Taking Account of the General Principles of Prevention. Formoso, C.T., Soibelman, L., De Cesare, C., Isatto, E.L., 2002. Material waste in building industry: main causes and prevention. J. Construct. Eng. Manage. 128 (4), 316–325. Frijters, A.C., Swuste, P.H., 2008. Safety assessment in design and preparation phase. Saf. Sci. 46 (2), 272–281. Gambatese, J.A., 2008. Research issues in prevention through design. J. Saf. Res. 39 (2), 153–156. Gambatese, J., Toole, T., Behm, M. 2008, March 9-11. Evolution of and Directions in Construction Safety and Health. Paper presented at 14th Rinker International Conference. Florida. Ghosh, S., Young-Corbett, D. 2009. Intersection between lean construction and safety research: a review of the literature. In Proceedings of the 2009 Industrial Engineering Research Conference (Vol. 30). Miami, FL, USA. Gonzalez-Delgado, M., Gómez-Dantés, H., Fernández-Niño, J.A., Robles, E., Borja, V. H., Aguilar, M., 2015. Factors associated with fatal occupational accidents among Mexican workers: a national analysis. PLoS ONE 10 (3). Haro, E., Kleiner, B.M., 2008. Macro ergonomics as an organizing process for systems safety. Appl. Ergon. 39 (4), 450–458.

This developed model is capable of predicting the minimizing of waste in construction projects during design phase by using safety system.  Safety system should be used during design phase to minimize waste (materials, time and cost) based on the model built in this study.  It is necessary to design training programs in safety field for design teams to increase their skills and knowledge to design for safety concept.  General and special conditions about safety requirement (plan, material, equipment, implementation methods, and schedule) must be confirmed in any CP.  For future research it is suggested to: o Investigate relationship between using safety system in maintenance phase and minimizing waste (materials, time and cost). o Building a computerized program to help the stakeholders of the project to calculate the relationship between the two variables (safety and waste). 6. Data availability The experimental data used to support the findings of this study are included in the article. Declaration of Competing Interest The authors declare that they have no known competing financial interests or personal relationships that could have appeared to influence the work reported in this paper.

9

K. Mahfuth, A. Loulizi, B.A. Tayeh et al.

Journal of King Saud University – Engineering Sciences xxx (xxxx) xxx

Hinze, J., Marini, J. 2008, March 9-11. Software to select design for safety suggestions. In Proc., CIB W99 2008 Int. Conf. on Evolution of and Directions in Construction Safety and Health. USA. Jo, B.W., Lee, Y.S., Kim, J.H., Khan, R.M.A., 2017. Trend analysis of construction industrial accidents in Korea from 2011 to 2015. Sustainability 9 (8), 1297. Katz, A., Baum, H., 2011. A novel methodology to estimate the evolution of construction waste in construction sites. Waste Manage. 31 (2), 353–358. Kawuwa, A.S., Adamu, M.A., Shehu, A., Abubakar, I.M., 2018. Health and Safety Challenges on Construction Sites of Bauchi Metropolis. Int. J. Sci. Res. Publ. 8, 367–377. Laitinen, H., Päivärinta, K., 2010. A new-generation safety contest in the construction industry–a long-term evaluation of a real-life intervention. Saf. Sci. 48 (5), 680–686. Mahfuth, K., Loulizi, A., Al Hallaq, K., Tayeh, B.A., 2019. Implementation phase safety system for minimising construction project waste. Buildings 9 (1), 25. Malekitabar, H., Ardeshir, A., Sebt, M.H., Stouffs, R., 2016. Construction safety risk drivers: A BIM approach. Saf. Sci. 82, 445–455. Manuele, F.A., 2008. Prevention through design (PtD): history and future. J. Saf. Res. 39 (2), 127–130. Micheli, G.J., Cagno, E., Calabrese, A., 2018. The transition from occupational safety and health (OSH) interventions to OSH outcomes: An empirical analysis of mechanisms and contextual factors within small and medium-sized enterprises. Int. J. Environ. Res. Public Health 15 (8), 1621. Muñiz, B., Peón, J., Ordás, C., 2007. Safety culture: Analysis of the causal relationships between its key dimensions. J. Saf. Res. 38, 627–641. Nagapan, S., Rahman, I.A., Asmi, A., 2012. Factors contributing to physical and nonphysical waste generation in construction industry. Int. J. Adv. Appl. Sci. 1 (1), 1–10. Nahmens, I., Ikuma, L.H., 2009. An Empirical Examination of the Relationship between Lean Construction and Safety in the Industrialized Housing Industry. Lean Construct. J. 1, 1–12. Nahmens, I., Ikuma, L.H., 2012. Effects of lean construction on sustainability of modular homebuilding. J. Archit. Eng. 18 (2), 155–163. Nahmens, I., Mullens, M.A., 2011. Lean homebuilding: Lessons learned from a precast concrete panelizer. J. Archit. Eng. 17 (4), 155–161. Nangan, I.I., Allen, P., Ganiron Jr, T.U., Martinez, D.T., 2017. Concrete Foundation Systems and Footings. World Scien. News 80, 1–17. Nazech, E. M., Zaldi, D., Trigunarsyah, B. 2008. Identification of construction waste in road and highway construction projects. Paper presented at 11th East AsiaPacific Conference on Engineering and Construction. Nordic council of ministries. 2017. Report of Safety & Health Construction Coordination. Nordic council of ministries. Denmark. Nordlöf, H., Wiitavaara, B., Winblad, U., Wijk, K., Westerling, R., 2015. Safety culture and reasons for risk-taking at a large steel-manufacturing company: Investigating the worker perspective. Saf. Sci. 73, 126–135.

Orihuela, P., Pacheco, S., Orihuela, J., 2017. Proposal of Performance Indicators for the Design of Housing Projects. Procedia Eng. 196, 498–505. Rwamamara, R., Holzmann, P. 2007. Oct 1.3. Reducing the human cost in construction through design. In Nordiska ergonomisällskapet. Paper presented at 39th Nordic Ergonomics Society Conference. Sweden. Shash, A., Ghazi, Sh., 2003. Construction equipment management practices of major contractors in Saudi Arabia. J. King Saud Univers. 16 (1), 61–80. Smallwood, J., 2008. The influence of architectural designers on construction ergonomics. Ergonom. SA: J. Ergonom. Soc. South Africa 20 (1), 40–55. Tayeh, B.A., Yaghi, R.O., Abu Aisheh, Y.I., 2020. Project manager interventions in occupational health and safety during the pre-construction phase in the Gaza Strip. Open Civil Eng. J. 14 (1), 20–30. Tayeh, B.A., Durdyev, S., Abuzuhri, I.O., Thurnell, D., 2019. Contractors’ attitudes towards the factors affecting sustainability performance: Evidence from Palestine. Buisiness Strategy Dev. 2 (3), 173–179. The Canadian integrated oil and natural gas company ‘‘Cenovus”, 2017. Contractor Health and Safety Program Requirement. Version 3.1. Toole, T.M., Gambatese, J., 2008. The trajectories of prevention through design in construction. J. Saf. Res. 39 (2), 225–230. Toole, T., Hervol, N., Hallowell, M. 2006. February 08-11. Designing steel for construction safety. In North American Steel Construction conference, San Antonio, TX (pp. 8-11). Vallentin, M. 2011. Probability and Statistics Cookbook, 12th ed.; Data Science Central: Georgia; Available online: http://pages.cs.wisc.edu/ tdw/files/cookbook-en.pdf (accessed on 19 January 2019). Village, J., Ostry, A., 2010. Assessing attitudes, beliefs and readiness for musculoskeletal injury prevention in the construction industry. Appl. Ergon. 41 (6), 771–778. Wang, J., Li, Z., Tam, V.W., 2014. Critical factors in effective construction waste minimization at the design stage: a Shenzhen case study, China. Resour. Conserv. Recycl. 82, 1–7. Wong, F.K., Chan, A.P., Wong, A.K., Hon, C.K., Choi, T.N., 2018. Accidents of electrical and mechanical works for public sector projects in Hong Kong. Int. J. Environ. Res. Public Health 15 (3), 485. Work Safe Victoria. 2005. Designing Safer Buildings and Structures ‘‘1st Edition”. Australia: Work Safe Victoria. Work Safe Victoria. 2007. Guide to the Workplace Health and Safety Obligations of Designers of Structures. ‘‘Version 1”. Australia: Work Safe Victoria. Zarges, T., Giles, B., 2008. Prevention through design (PtD). J. Saf. Res. 39 (2), 123– 126. Zhao, Z.Y., Lv, Q.L., Zuo, J., Zillante, G., 2010. Prediction system for change management in construction project. J. Construct. Eng. Manage. 136 (6), 659– 669.

10

Similar documents

jurnal internasional 4

Ilham Nur Azizi - 683.2 KB

Modul 4 Pajak Internasional

Winda Oktasari - 166.5 KB

4. SUBJEK HUKUM INTERNASIONAL

Muhammad Farhan Ghibran - 529.2 KB

jurnal internasional 2

Ilham Nur Azizi - 1.2 MB

jurnal internasional 5

Ilham Nur Azizi - 963.5 KB

jurnal internasional 3

Ilham Nur Azizi - 1.2 MB

JURNAL NURUL 4

Inge Dwi Wahyunii - 107.3 KB

BAB 4 JURNAL

Hafidz Setyo - 134.6 KB

Jurnal Radiologi (4)

Andrean Heryanto - 4.3 MB

Kel 4 201910601038 Rohinoor Intan Jurnal 4

ROHINOOR INTAN BERLIANA ROHINOOR INTAN BERLIANA - 454.6 KB

049_Tiara Ayu Dwi Novitasari_REVIEW JURNAL INTERNASIONAL

Tiara Ayu Dwi Novitasari - 680.8 KB

© 2024 VDOCS.RO. Our members: VDOCS.TIPS [GLOBAL] | VDOCS.CZ [CZ] | VDOCS.MX [ES] | VDOCS.PL [PL] | VDOCS.RO [RO]